Project description:
As Senior Project Manager, managed and supervised the design, budget, documents/project controls, scheduling support, estimating, cost analysis, change order negotiations, claim analysis and claim documentation support to the project management team. Analyzed a complex acceleration on a claims submitted by the general Contractor and its subcontractors. Performed detailed schedule analyses, measured mile analyses, “what-if” scenarios, and critical path delay analyses. Prepared and demonstrated graphical schedule and actual cost impact analyses to define and illustrate labor and equipment hours. Successfully completed a negotiated settlement for the LAWA South Runway Improvements Project, which eliminated further delays in the completion of the project.